Five Year Outlook

Corridor Wide Materials Estimate Calendar Years 2024 - 2029

Details Here

Major items summary

Material

2025

2026

2027

2028

2029

2030

Asphalt (ton)

32,900

96,000

99,100

127,200

144,400

216,000

Aggregate (ton)

31,800

95,300

101,600

128,200

153,000

190,200

Pipe (linear feet)

5,550

16,660

16,620

17,560

18,370

27,390

Guardrail (linear feet)

5,800

18,300

19,200

26,700

31,400

44,100

Material 2024 - 2029
Structures (each) 40
  • Years shown are in Calendar Year.
  • Assumed I-81 corridor projects in Bristol, Staunton, and Salem Districts with Project Construction Costs over $15 M, and Construction occurring between calendar years 2024-2029. Only quantities in the 3rd and 4th quarter of 2024 are included.
  • Does not include projects already under contract.
  • Only major materials/items commonly used for the I-81 Program are considered.
  • Quantity estimates are used to extract materials/quantities information for the projects that are currently in design i.e., Preliminary Field Investigation (PFI), Public Hearing (PH), Field Investigation (FI), Right of Way (RW), etc. as applicable.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Major Quantities Corridor-Wide
Calendar Years 2024 - 2029

Item

Bristol Details

Salem Details

Staunton Details

Grand Total

Category

Item Description

Unit

Quantity

Drainage

Box Culvert (Any Size)

linear feet

0

1,450

350

1,800

Conc. Pipes Under 36"

linear feet

70

58,240

28,950

87,260

Conc. Pipes Over 36"

linear feet

0

7,230

1,200

8,430

Jacked & Bored Pipes Under 36"

linear feet

0

1,630

1,400

3,030

Jacked & Bored Pipes Over 36"

linear feet

0

1,360

270

1,630

Manhole & Inlets

linear feet

7

610

400

1,017

Endsection & Endwalls

linear feet

30

310

100

440

Curb & Gutter

ton

210

7,760

6,800

14,770

Pavement

Asphalt (Any Type)

ton

4,500

392,300

318,800

715,600

Aggregate

linear feet

39,700

315,700

354,700

700,100

Traffic and Safety

Guardrail (Any Type)

linear feet

2,300

84,200

59,000

145,500

End Treatment (Any Type)

linear feet

30

140

170

340

Concrete Barrier - Temporary

linear feet

4,400

376,300

228,700

609,400

Concrete Barrier - Permanent

linear feet

0

34,200

50,900

85,100

Structures

*Bridge ( Deck Area)

square feet

7,900

110,400

192,100

310,400

Noise Barrier Wall

square feet

0

586,900

685,100

1,272,000

Retaining Wall

square feet

10,400

14,900

4,800

30,100

 

*Number of bridges for

Bridge Replacement

Bridge Widening

Bristol District

0

1

Salem District

15

1

Staunton District

10

8

  • Years shown are in Calendar Year.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Asphalt

Asphalt Tonnage per District (2024 - 2029)
In thousands



Bar Graph showing Asphalt per District
  • Years shown are in Calendar Year.
« Back to intro screen

Aggregate

Aggregate Tonnage per District (2024 - 2029)
In thousands



Bar Graph showing Aggregate per District
  • Years shown are in Calendar Year.
« Back to intro screen

Pipe

Linear Feet of Pipe per District (2024 - 2029)
In thousands



Bar Graph showing Pipe per District
  • Years shown are in Calendar Year.
« Back to intro screen

Guardrail

Linear Feet of Guardrail per District (2024 - 2029)
In thousands



Bar Graph showing Guardrails per District
  • Years shown are in Calendar Year.
« Back to intro screen

Structures

Bridge Repair and Replacement Counts per District



Bar Graph showing Bridges per District
  • Years shown are in Calendar Year.
« Back to intro screen

Bristol

  • Years shown are in Calendar Year.
  • Project(s) included in Bristol District are anticipated to be completed by Year 2027.
« Back to intro screen

Staunton

  • Years shown are in Calendar Year.
« Back to intro screen

Salem

  • Years shown are in Calendar Year.
« Back to intro screen

Overview

  • Years shown are in Calendar Year.

July 2024 Update – Data for planning purposes only, data subject to change.

Last updated: December 24, 2024

Alert Icon

Please note that this file is not ADA compliant. Choose one of below options: