Five Year Outlook

Corridor Wide Materials Estimate Calendar Years 2024 - 2029

Details Here

Major items summary

Material

2024

2025

2026

2027

2028

2029

Asphalt (ton)

16,200

93,900

130,500

169,400

190,800

181,100

Aggregate (ton)

5,700

62,200

98,200

118,700

129,800

130,400

Pipe (linear feet)

1,170

12,950

18,440

23,560

25,090

24,450

Guardrail (linear feet)

5,700

22,900

29,100

35,600

41,300

39,500

Material 2024 - 2029
Structures (each) 40
  • Years shown are in Calendar Year.
  • Assumed I-81 corridor projects in Bristol, Staunton, and Salem Districts with Project Construction Costs over $15 M, and Construction occurring between calendar years 2024-2029. Only quantities in the 3rd and 4th quarter of 2024 are included.
  • Does not include projects already under contract.
  • Only major materials/items commonly used for the I-81 Program are considered.
  • Quantity estimates are used to extract materials/quantities information for the projects that are currently in design i.e., Preliminary Field Investigation (PFI), Public Hearing (PH), Field Investigation (FI), Right of Way (RW), etc. as applicable.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Major Quantities Corridor-Wide
Calendar Years 2024 - 2029

Item

Bristol Details

Salem Details

Staunton Details

Grand Total

Category

Item Description

Unit

Quantity

Drainage

Box Culvert (Any Size)

linear feet

0

1,360

720

2,080

Conc. Pipes Under 36"

linear feet

70

58,090

30,100

88,260

Conc. Pipes Over 36"

linear feet

0

7,360

3,430

10,790

Jacked & Bored Pipes Under 36"

linear feet

0

1,550

1,330

2,880

Jacked & Bored Pipes Over 36"

linear feet

0

2,140

270

2,410

Manhole & Inlets

linear feet

7

610

400

1,017

Endsection & Endwalls

linear feet

30

300

230

560

Curb & Gutter

ton

210

8,270

6,580

15,060

Pavement

Asphalt (Any Type)

ton

4,800

414,600

362,500

781,900

Aggregate

linear feet

31,100

315,800

198,100

545,000

Traffic and Safety

Guardrail (Any Type)

linear feet

2,300

85,600

86,200

174,100

End Treatment (Any Type)

linear feet

30

160

260

450

Concrete Barrier - Temporary

linear feet

4,600

372,800

300,200

677,600

Concrete Barrier - Permanent

linear feet

0

37,600

40,000

77,600

Structures

*Bridge ( Deck Area)

square feet

7,900

95,800

184,900

288,600

Noise Barrier Wall

square feet

0

536,100

355,100

891,200

Retaining Wall

square feet

10,800

17,700

4,500

33,000

 

*Number of bridges for

Bridge Replacement

Bridge Widening

Bristol District

0

1

Salem District

15

1

Staunton District

11

12

  • Years shown are in Calendar Year.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Asphalt

Asphalt Tonnage per District (2024 - 2029)
In thousands



Bar Graph showing Asphalt per District
  • Years shown are in Calendar Year.
« Back to intro screen

Aggregate

Aggregate Tonnage per District (2024 - 2029)
In thousands



Bar Graph showing Aggregate per District
  • Years shown are in Calendar Year.
« Back to intro screen

Pipe

Linear Feet of Pipe per District (2024 - 2029)
In thousands



Bar Graph showing Pipe per District
  • Years shown are in Calendar Year.
« Back to intro screen

Guardrail

Linear Feet of Guardrail per District (2024 - 2029)
In thousands



Bar Graph showing Guardrails per District
  • Years shown are in Calendar Year.
« Back to intro screen

Structures

Bridge Repair and Replacement Counts per District



Bar Graph showing Bridges per District
  • Years shown are in Calendar Year.
« Back to intro screen

Bristol

  • Years shown are in Calendar Year.
  • Project(s) included in Bristol District are anticipated to be completed by Year 2027.
« Back to intro screen

Staunton

  • Years shown are in Calendar Year.
« Back to intro screen

Salem

  • Years shown are in Calendar Year.
« Back to intro screen

Overview

  • Years shown are in Calendar Year.

July 2024 Update – Data for planning purposes only, data subject to change.

Last updated: July 18, 2024

Alert Icon

Please note that this file is not ADA compliant. Choose one of below options: