Skip to main content

Five Year Outlook

Corridor Wide Materials Estimate Calendar Years 2026 - 2031

Details Here

Major items summary

Material

2026

2027

2028

2029

2030

2031

Asphalt (ton)

0

0

16,500

31,500

157,500

157,500

Aggregate (ton)

0

0

16,100

37,200

112,700

112,700

Pipe (linear feet)

0

0

370

860

14,140

14,090

Guardrail (linear feet)

0

0

4,800

8,900

31,500

31,500

Material 2026 - 2031
Structures (each) 10
  • Years shown are in Calendar Year.
  • Assumed I-81 corridor projects in Bristol, Staunton, and Salem Districts with Project Construction Costs over $15 M, and Construction occurring between calendar years 2026-2031.
  • Does not include projects already under contract.
  • Only major materials/items commonly used for the I-81 Program are considered.
  • Quantity estimates are used to extract materials/quantities information for the projects that are currently in design i.e., Preliminary Field Investigation (PFI), Public Hearing (PH), Field Investigation (FI), Right of Way (RW), etc. as applicable.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Major Quantities Corridor-Wide
Calendar Years 2025 - 2030

Item

Bristol Details

Salem Details

Staunton Details

Grand Total

Category

Item Description

Unit

Quantity

Drainage

Box Culvert (Any Size)

linear feet

N/A

20

430

450

Conc. Pipes Under 36"

linear feet

N/A

21,950

2,450

24,400

Conc. Pipes Over 36"

linear feet

N/A

1,820

1,220

3,040

Jacked & Bored Pipes Under 36"

linear feet

N/A

620

240

860

Jacked & Bored Pipes Over 36"

linear feet

N/A

460

250

710

Manhole & Inlets

linear feet

N/A

260

130

390

Endsection & Endwalls

linear feet

N/A

120

60

180

Curb & Gutter

ton

N/A

2,980

1,240

4,220

Pavement

Asphalt (Any Type)

ton

N/A

223,400

139,600

363,000

Aggregate

linear feet

N/A

103,600

175,100

278,700

Traffic and Safety

Guardrail (Any Type)

linear feet

N/A

37,600

39,100

76,700

End Treatment (Any Type)

linear feet

N/A

80

70

150

Concrete Barrier - Temporary

linear feet

N/A

195,000

84,800

279,800

Concrete Barrier - Permanent

linear feet

N/A

12,200

13,900

26,100

Structures

*Bridge ( Deck Area)

square feet

N/A

4,400

77,400

81,800

Noise Barrier Wall

square feet

N/A

85,400

220,300

305,700

Retaining Wall

square feet

N/A

11,200

0

11,200

 

*Number of bridges for

Bridge Replacement

Bridge Widening

Bristol District

N/A

N/A

Salem District

1

0

Staunton District

9

0

  • Years shown are in Calendar Year.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Asphalt

Asphalt Tonnage per District (2026 - 2031)
In thousands



Bar Graph showing Asphalt per District
  • Years shown are in Calendar Year.
« Back to intro screen

Aggregate

Aggregate Tonnage per District (2026 - 2031)
In thousands



Bar Graph showing Aggregate per District
  • Years shown are in Calendar Year.
« Back to intro screen

Pipe

Linear Feet of Pipe per District (2026 - 2031)
In thousands



Bar Graph showing Pipe per District
  • Years shown are in Calendar Year.
« Back to intro screen

Guardrail

Linear Feet of Guardrail per District (2026 - 2031)
In thousands



Bar Graph showing Guardrails per District
  • Years shown are in Calendar Year.
« Back to intro screen

Structures

Bridge Repair and Replacement Counts per District



Bar Graph showing Bridges per District
  • Years shown are in Calendar Year.
« Back to intro screen

Bristol

  • Years shown are in Calendar Year.
  • Project(s) included in Bristol District are anticipated to be completed by Year 2027.
« Back to intro screen

Staunton

  • Years shown are in Calendar Year.
« Back to intro screen

Salem

  • Years shown are in Calendar Year.
« Back to intro screen

Overview

  • Years shown are in Calendar Year; 2026 includes July through December only.

December 2025 Update – Data for planning purposes only, data subject to change.

Last updated: January 15, 2026

Please note that this file is not ADA compliant. Choose one of below options: