Five Year Outlook

Corridor Wide Materials Estimate Calendar Years 2025 - 2030

Details Here

Major items summary

Material

2025

2026

2027

2028

2029

2030

Asphalt (ton)

36,200

107,200

107,200

125,900

150,500

252,900

Aggregate (ton)

25,800

84,400

84,400

94,100

131,000

178,300

Pipe (linear feet)

5,830

17,490

17,490

18,100

19,140

29,960

Guardrail (linear feet)

5,100

16,100

16,100

21,200

27,800

45,500

Material 2025 - 2030
Structures (each) 35
  • Years shown are in Calendar Year; 2025 includes July through December only.
  • Assumed I-81 corridor projects in Bristol, Staunton, and Salem Districts with Project Construction Costs over $15 M, and Construction occurring between calendar years 2025-2030.
  • Does not include projects already under contract.
  • Only major materials/items commonly used for the I-81 Program are considered.
  • Quantity estimates are used to extract materials/quantities information for the projects that are currently in design i.e., Preliminary Field Investigation (PFI), Public Hearing (PH), Field Investigation (FI), Right of Way (RW), etc. as applicable.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Major Quantities Corridor-Wide
Calendar Years 2025 - 2030

Item

Bristol Details

Salem Details

Staunton Details

Grand Total

Category

Item Description

Unit

Quantity

Drainage

Box Culvert (Any Size)

linear feet

0

1,130

340

1,670

Conc. Pipes Under 36"

linear feet

50

62,190

30,590

92,830

Conc. Pipes Over 36"

linear feet

0

7,320

1,030

8,350

Jacked & Bored Pipes Under 36"

linear feet

0

1,680

1,490

3,170

Jacked & Bored Pipes Over 36"

linear feet

0

1,790

200

1,990

Manhole & Inlets

linear feet

5

660

500

1,165

Endsection & Endwalls

linear feet

5

320

130

455

Curb & Gutter

ton

210

9,940

6,640

16,790

Pavement

Asphalt (Any Type)

ton

5,400

466,100

308,400

779,900

Aggregate

linear feet

32,200

323,800

242,000

598,000

Traffic and Safety

Guardrail (Any Type)

linear feet

2,100

77,500

52,200

131,800

End Treatment (Any Type)

linear feet

30

250

210

490

Concrete Barrier - Temporary

linear feet

4,100

431,900

224,300

660,300

Concrete Barrier - Permanent

linear feet

0

27,700

49,800

77,500

Structures

*Bridge ( Deck Area)

square feet

8,100

142,900

159,500

310,000

Noise Barrier Wall

square feet

0

392,400

565,800

958,200

Retaining Wall

square feet

11,500

179,400

12,600

203,500

 

*Number of bridges for

Bridge Replacement

Bridge Widening

Bristol District

0

1

Salem District

15

1

Staunton District

10

8

  • Years shown are in Calendar Year; 2025 includes July through December only.
  • It is assumed that construction sequence will depend on contractor’s construction means and method. Hence the quantities are broken down equally per quarter and do not account for the construction sequence except for Temporary Traffic Barrier.
  • It is assumed that 100% of Temporary Traffic Control items will be utilized in the first year of construction.
« Back to intro screen

Asphalt

Asphalt Tonnage per District (2025 - 2030)
In thousands



Bar Graph showing Asphalt per District
  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Aggregate

Aggregate Tonnage per District (2025 - 2030)
In thousands



Bar Graph showing Aggregate per District
  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Pipe

Linear Feet of Pipe per District (2025 - 2030)
In thousands



Bar Graph showing Pipe per District
  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Guardrail

Linear Feet of Guardrail per District (2025 - 2030)
In thousands



Bar Graph showing Guardrails per District
  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Structures

Bridge Repair and Replacement Counts per District



Bar Graph showing Bridges per District
  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Bristol

  • Years shown are in Calendar Year; 2025 includes July through December only.
  • Project(s) included in Bristol District are anticipated to be completed by Year 2027.
« Back to intro screen

Staunton

  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Salem

  • Years shown are in Calendar Year; 2025 includes July through December only.
« Back to intro screen

Overview

  • Years shown are in Calendar Year; 2025 includes July through December only.

June 2025 Update – Data for planning purposes only, data subject to change.

Last updated: June 27, 2025